How to Shade Your Deck

Updated: Jul. 27, 2023

A simple shelter for you and your deck—and your burgers!

FH03MAR_05022_026-2Family Handyman

You don't have to let the blazing sun or drippy weather drive you indoors. This simple covered pergola will keep you comfortable long after your neighbors with unsheltered decks have given up and gone inside.

We designed it for versatility and easy construction. Its 10 x 10-ft. size is large enough to accommodate a table and chairs but small and light enough not to require extra footings or deck framing. We recommend that your deck have at least 2x8 joists to ensure adequate strength. In addition, we made posts and beams from 2-by lumber because it's lighter than timbers and much easier to fasten together. You can expand the length and width about 25 percent without going to stronger components. We designed the fabric cover to be easily removable during cold months.

You might also like: TBD

Time
Multiple Days
Complexity
Intermediate
Cost
$501-1000

One person can build and stain the entire structure in about six days.

We built our pergola from standard construction cedar because it’s weather resistant and accepts stain well. Other rot-resistant wood would work as well. Allow about three weekends for completion, including staining.

A pergola like this looks best on a larger deck, one at least twice the size of the pergola. If you have doubts,mock up the corners with braced 2x4s; stand back and imagine the rest. If necessary, alter the slope of the rafters to match your house. (You’ll have to recalculate the rafter angles and lengths.)

In this article, we’ll walk you through the construction details, especially how to make solid connections to your deck. This is a surprisingly easy project to build; it mostly involves cutting the pieces and assembling them with nails and screws. You should have confidence handling a circular saw and level, as well as simple carpentry experience. You can sew the fabric yourself or have an awning shop do it for you. Apply for a building permit; take a sketch of your existing deck structure as well as this plan for approval by the inspector.

Step 1: Cut all the components to size

Cut all the components to size (see Figure A and the Cutting List). Nail together the four corner posts (parts A1 and A2) with pairs of 3-in. hot-dipped galvanized box nails spaced 2 ft. apart. Fasten the ridge post (part G) with four nails to the cross beam 2×6 (part D1). There are three of these assemblies. Be sure the post is square to the cross beam.

To save time, stain the wood before assembly

First cut all the parts for the pergola, using the Cutting List. Next nail together the four corner posts with pairs of 3-in. galvanized nails. Nail the three ridge posts to three 2×6 cross beam members.

Step 2: Position five 2×2 blocks on the 2×8 post beam member

Position five 2×2 blocks (part B2) on the 2×8 post beam member (for the layout, see Figure A , Post Beam Detail). Fasten each block with a couple of nails. Be sure the blocks are flush with the bottom of the beam. Finally, stain all the parts and set them aside to dry.

Then nail the 2×2 x 12- 1/4 in. blocks to one side of two 2×8 post beam members. It’s much easier and faster to stain all the parts before assembly. Let them completely dry before assembling.

Step 3: Cut two pieces of 1×4, each 10 ft. long, and two pieces 9 ft. 5 in. long

Cut two pieces of 1×4, each 10 ft. long, and two pieces 9 ft. 5 in. long. Butt the shorter pieces between the 10-footers and drive 1-1/4 in. screws through corner blocks to connect the sides. Tack one side of the frame to the deck and then adjust the frame until the two diagonals are the same length. Fasten a 1×4 angled brace to hold the frame rigid and square.

Assemble a template to position the corners

Build a 10 x 10-ft. template out of 1x4s to help position the corner posts accurately. Screw this frame together so you can disassemble it later, and use the 1x4s to temporarily brace the posts. Shift the template around on your deck to help visualize the best location for the pergola.

Removing deck boards at the corner post positions can be difficult if they’re nailed rather than screwed to the joists. If possible, get underneath the deck and knock the deck boards up with a heavy hammer. If you’re lucky, the boards will pull the nails up with them.Most likely, however, the nails will pull through or split the boards, so you may have to replace several boards.

Build the pockets for the four corner posts

Fasten blocking between the deck joists to support each corner post. Use the template to accurately locate the edges of the corner posts (Figure B).Mark the position of the 2×4 center that extends down between the deck joists (Figure B). Make sure the 2×4 doesn’t land on top of a joist. The one we show sits against the side of a joist.

Step 4: Remove enough deck boards to access the joists at the corners of the template

Remove enough deck boards to access the joists at the corners of the template. Position the template exactly and mark the outside edge of the corner on the deck boards and joists. Then mark the position of the 2×4 post center (see Figure B).

Step 5: Lay out the position of the center 2×4

Lay out the position of the center 2×4 and nail 2×8 joist hangers on each side of it. Nail or screw the 2×8 supports in place.

Be sure to use joist hangers to ensure the strength of the blocks you’re adding. It can be tricky finding room to swing a hammer to drive the hanger nails. In some situations, you may have better luck driving screws. Although the 2×4 center slides into the pocket, the post’s 2×6 components sit on top of the joist blocks (Step 6), which support the weight of the pergola.

Step 6: Cut a 3-3/4 in. long treated 2×4 block

Cut a 3-3/4 in. long treated 2×4 block and screw it between the joist blocks to complete the support.

Step 7: Drop the four posts into the joist pockets

Assemble the pergola

Drop the posts into the pockets and drive four 3-in. nails to secure each of them to the blocking. Don’t worry if they seem wobbly; the rest of the pergola structure will stiffen them. Finally, plumb each post in both directions and secure with two temporary braces.Use the 1×4 salvaged from the template. Screw short pieces of 2×4 to the deck to anchor the bottom of the braces.

Step 8: Set the 2×8 beam with the 2×2 blocks onto the post’s 2×6 shoulder

Set the 2×8 beam with the 2×2 blocks onto the post’s 2×6 shoulder and nail into place with four 3-in. nails. Position the second 2×8 and nail it into the posts. Finally drive two nails through the second 2×8 and into each 2×2 block.

Next to go up are the two 2x8s that make up each post beam. Screw a temporary holder to one of the posts if you do this by yourself. A helper on a second ladder makes the job quicker.

Step 9: Position the three 2×2 cross beam blocks (part D2) to the inside of the beam

Position the three 2×2 cross beam blocks (part D2) to the inside of the beam. See Figure A , Post Beam Detail. Drill 3/8-in. clearance holes through the 2x2s and 1/4-in. pilot holes into the beam; drive 3/8-in. by 4-in. galvanized lag screws.

Use galvanized lag screws with flat washers to fasten the cross beam blocks to the side of the beams. Strength is critical here, so don’t use deck screws or nails.

Step 10: Lift the 2×6 cross beam and ridge post into place and drive three screws at each end

Fasten the double 2×6 cross beams into both the block and the beam .Drill clearance holes to avoid splitting, and drive 3-in. deck screws. Drive two 3/8 x 4-in. galvanized lag screws through the outer 2×6 and the ridge post into the inner 2×6. This securely pins the ridge posts to both 2x6s.

Step 11: Slide the top end of the angle brace between the beam’s two components

The angle braces at each corner slide between the two members that make up the beams. If the space is too tight for the brace to slide in, wedge open the space a bit. After the brace is in, remove the wedge. Make sure the bottoms of the two braces are even with each other at each corner. Drill clearance and pilot holes, and drive lag screws to secure them (see photo for sizes and location). Now you can remove the temporary corner braces.

Step 12: Slide the ridge beam into the post notches and center it end to end

Lay out the rafter positions on both sides of the ridge beam before setting it in place. It’s a lot easier to do this while standing on the ground than on a ladder. Now set the ridge into the three ridge post slots.

Step 13: Set a rafter against the ridge beam, holding it 1-1/2 in. below the top edge

Work from one end to the other setting the rafters. Make sure that each rafter sits 1-1/2 in. below the top of the ridge beam. Fasten all the rafters to the ridge beam first, then go back and fasten them to the post beams.

Step 14: Make layout lines every 16 in. along the top edge of the rafters

Starting at the ridge, mark out 16-in. spacing for the purlins. You don’t need to mark out all the rafters, just both end rafters and the center one. Position the 2x2s on the layout marks and drive a single 3-in. galvanized nail through the purlin into both the end rafters and the center one. Next have a helper look down the length of the purlin from one end and sight it straight as you nail off the purlin at the rest of the rafters.

Step 15: Unroll the canvas over the top of the purlins

Install the canvas cover

We used a fabric manufactured specifically for awnings. It’s UV stable and rot-proof. Canvas is a less expensive choice, but it’s not as long lasting. You’ll have to sew four strips together to get the 12-ft. width. The sewing takes some experience and a heavy-duty sewing machine. If necessary, have a tent and awning company make the cover for you.

The fabric cover is 144 in. wide by 174 in. long with pipe pockets sewn in at the two bottom edges (Figure C). Make and attach three 1-in. wide by 10-in. long fabric straps on each side centered on the double rafters. Sew on Velcro strips to finish them.

Fabricate a 12-ft. length of 1/2-in. EMT conduit (metal electric conduit). It comes in 10-ft. pieces, so you’ll need to cut it (use a hacksaw) to add a 2-ft. piece. Connect the two sections with a 12-in. piece of 5/8-in. diameter wood dowel. Apply polyurethane glue or construction adhesive to each end of the dowel, then slide half of it into each piece of pipe. Let the glue set overnight.

Now slide the pipes into the completed awning cover. The pipes make it easy to roll up the fabric.

Start at one edge and roll it up with the finished side of the fabric showing.

We used 3-1/2 in. galvanized nails for the strap anchors (Photo detail). Drill a clearance hole through one of the rafters; slide the nail through until its tip hits the second rafter. Then hammer it in. The Velcro strap wraps around the nail and sticks to itself.

Working from a stepladder, set the rolled-up cover on top of the rafters along one lower edge. Unroll it up the rafters to the top, then down the other side.

Additional Information